Home » » LAMPIRAN F FORM COMMISSIONING AHU

LAMPIRAN F FORM COMMISSIONING AHU

F.1 TUJUAN

Form ini digunakan untuk:

✓ Verifikasi instalasi AHU

✓ Verifikasi performa AHU

✓ Dokumentasi commissioning

✓ Dasar serah terima sistem

✓ Referensi maintenance dan troubleshooting


FORM F-01

AHU COMMISSIONING DATA SHEET

ItemData
Project Name
Client
Location
AHU Tag Number
AHU Type
Airflow Design (CMH)
Static Pressure Design (Pa)
Motor Power (kW)
Cooling Capacity
Filter Configuration
Date
Commissioning Engineer

FORM F-02

PRE-COMMISSIONING CHECKLIST

Mechanical Inspection

NoItemStatusRemark
1AHU Installed Correctly□ OK □ NG
2Access Door Installed□ OK □ NG
3Filter Installed□ OK □ NG
4Coil Installed□ OK □ NG
5Drain Pan Installed□ OK □ NG
6Drain Trap Installed□ OK □ NG
7Fan Rotation Correct□ OK □ NG
8Flexible Connection Installed□ OK □ NG
9Duct Connected Properly□ OK □ NG
10Damper Installed□ OK □ NG

Electrical Inspection

NoItemStatusRemark
1Panel Installed□ OK □ NG
2MCCB Installed□ OK □ NG
3Grounding Connected□ OK □ NG
4Motor Protection Installed□ OK □ NG
5Sensor Connected□ OK □ NG
6VFD Connected□ OK □ NG
7Emergency Stop Tested□ OK □ NG

Instrument Inspection

NoItemStatusRemark
1Temperature Sensor□ OK □ NG
2RH Sensor□ OK □ NG
3Differential Pressure Sensor□ OK □ NG
4Airflow Sensor□ OK □ NG
5Magnehelic Gauge□ OK □ NG

FORM F-03

FUNCTIONAL TEST REPORT

NoFunctionResultRemark
1Fan Start□ Pass □ Fail
2Fan Stop□ Pass □ Fail
3Cooling Coil Control□ Pass □ Fail
4Heater Control□ Pass □ Fail
5UV-C Operation□ Pass □ Fail
6Alarm Function□ Pass □ Fail
7Sensor Reading□ Pass □ Fail
8Damper Operation□ Pass □ Fail

FORM F-04

AIRFLOW MEASUREMENT REPORT

PointLocationVelocity (m/s)Area (m²)Airflow (CMH)
1
2
3
4
5

Total Airflow

Design Airflow :

__________ CMH

Measured Airflow :

__________ CMH

Deviation :

__________ %

Status :

□ PASS

□ FAIL


FORM F-05

AIR CHANGE RATE (ACH) REPORT

Room Information

ItemValue
Room Name
Length (m)
Width (m)
Height (m)
Room Volume (m³)
Airflow (CMH)
ACH Design
ACH Actual

Result:

□ PASS

□ FAIL


FORM F-06

DIFFERENTIAL PRESSURE REPORT

RoomPressure Design (Pa)Pressure Actual (Pa)Status
Room 1
Room 2
Room 3
Room 4

Result:

□ PASS

□ FAIL


FORM F-07

TEMPERATURE & RH REPORT

RoomTemp Design (°C)Temp Actual (°C)RH Design (%)RH Actual (%)
Room 1
Room 2
Room 3
Room 4

Result:

□ PASS

□ FAIL


FORM F-08

ELECTRICAL PERFORMANCE REPORT

ParameterDesignActual
Voltage (V)
Current (A)
Frequency (Hz)
Motor Power (kW)
Fan RPM

Remarks:



FORM F-09

FILTER PRESSURE DROP REPORT

Filter StageInitial (Pa)Actual (Pa)Status
Pre Filter
Medium Filter
Final Filter
HEPA Filter

FORM F-10

HEPA INTEGRITY TEST REPORT

Filter Information

ItemData
Filter Type
Filter Grade
Filter Location
Serial Number

PAO / DOP Test Result

Filter IDResult
HEPA-01□ Pass □ Fail
HEPA-02□ Pass □ Fail
HEPA-03□ Pass □ Fail

Remarks:



FORM F-11

SMOKE TEST REPORT

Test ItemResult
Airflow Direction Verified□ Pass □ Fail
No Reverse Flow□ Pass □ Fail
No Dead Zone□ Pass □ Fail
No Excessive Turbulence□ Pass □ Fail

Observations:




FORM F-12

PARTICLE COUNT REPORT

LocationISO Class DesignResult
Point 1
Point 2
Point 3
Point 4

Overall Status:

□ PASS

□ FAIL


FORM F-13

CLEANROOM RECOVERY TEST REPORT

ItemValue
Room Name
ISO Classification
Disturbance Method
Recovery Time Design
Recovery Time Actual

Result:

□ PASS

□ FAIL


FORM F-14

FINAL COMMISSIONING SUMMARY

Scope Performed

□ Airflow Test

□ ACH Verification

□ Differential Pressure Test

□ Temperature Verification

□ RH Verification

□ Electrical Verification

□ Filter Pressure Drop Verification

□ HEPA Integrity Test

□ Smoke Test

□ Particle Count

□ Recovery Test


Overall Result

□ ACCEPTED

□ ACCEPTED WITH COMMENT

□ REJECTED


Comments





Signatures

Commissioning Engineer

Name :


Signature :


Date :



Client Representative

Name :


Signature :


Date :



RIJOMAC COMMISSIONING PACKAGE

BASIC HVAC

✓ Airflow

✓ Temperature

✓ RH

✓ Electrical Check


CLEANROOM COMMISSIONING

✓ Airflow

✓ ACH

✓ Differential Pressure

✓ Particle Count

✓ HEPA Integrity

✓ Smoke Test

✓ Recovery Test


MEDICAL HVAC COMMISSIONING

✓ ACH

✓ Differential Pressure

✓ HEPA Integrity

✓ Airflow Direction


BSL LABORATORY COMMISSIONING

✓ Pressure Cascade

✓ HEPA Integrity

✓ Smoke Study

✓ Exhaust Verification

✓ Containment Verification


PRINSIP RIJOMAC

"Troubleshooting bukan menebak."

"Commissioning bukan asumsi."

"Data adalah bukti bahwa sistem bekerja sesuai desain."